Sites info
- Construction of lot 3 - La Forêt des Groues - ZAC des Groues Nov 19, 2021 - Jun 30, 2024
- Construction of lot 4 - Flora - ZAC des Groues Dec 1, 2021 - Jun 30, 2024
- LIGHTWELL Project Apr 1, 2022 - Jun 30, 2024
- Boulevard Circulaire Patrick Devedjian - Retaining wall work Aug 1, 2022 - Aug 1, 2024
- Paris La Défense redevelops rue Jules Ferry and rue Fauvelles around the future Engie Campus Jul 1, 2023 - Oct 31, 2024
- Construction of the FOcd lot - ZAC des Groues Jan 3, 2022 - Dec 31, 2024
- Public space works on the Balcony - ZAC de Groues Oct 1, 2021 - Jan 1, 2025
- Construction of Lot 1 - West Village - ZAC des Groues Dec 31, 2021 - Jan 31, 2025
- Quartier de Charlebourg, à la Garenne-Colombes : début des travaux Jun 8, 2020 - Jun 30, 2025
- Construction of lot 2 - Les Hallizées May 1, 2023 - Sep 30, 2025
- Work on public spaces at Jardin des Rails, rue Edouard Colonne and Place des Groues Oct 1, 2023 - Dec 31, 2025
- Odyssey project site - Les Miroirs site Dec 15, 2021 - Jan 31, 2026
- Redevelopment of the public spaces of the Place Carpeaux Jan 1, 2022 - Jan 31, 2028
Edenn site
Oct 25, 2023 - Mar 31, 2024
Summary of work carried out
The year 2023 was marked by the completion of the geothermal network, the shotcrete walls, the erection of the cranes and the living quarters on gantry cranes, and finally by the ground breaking for the structure of the first 3 basement levels, garden level and ground floor.
Work scheduled for the first quarter of 2024
- Carrying out the structural work: vertical and horizontal structures in concrete and metal framework for the end of the ground floor and the first floor, then in wood for the second floor;
- Insulation and waterproofing work on the infrastructure levels; Insulation and waterproofing work on the infrastructure levels; * Start-up of the technical trades in the basement and garden level;
- Start-up of the garden level facades.
Information on the context of the project and site news is available on the Edenn application, which can be downloaded from App Store and Google Play. The site team can be contacted at edenn.riverains@vinci-construction.fr.