Sites info
- Construction of lot 3 - La Forêt des Groues - ZAC des Groues Nov 19, 2021 - Jun 30, 2024
- Construction of lot 4 - Flora - ZAC des Groues Dec 1, 2021 - Jun 30, 2024
- LIGHTWELL Project Apr 1, 2022 - Jun 30, 2024
- Boulevard Circulaire Patrick Devedjian - Retaining wall work Aug 1, 2022 - Aug 1, 2024
- Paris La Défense redevelops rue Jules Ferry and rue Fauvelles around the future Engie Campus Jul 1, 2023 - Oct 31, 2024
- Construction of the FOcd lot - ZAC des Groues Jan 3, 2022 - Dec 31, 2024
- Public space works on the Balcony - ZAC de Groues Oct 1, 2021 - Jan 1, 2025
- Construction of Lot 1 - West Village - ZAC des Groues Dec 31, 2021 - Jan 31, 2025
- Quartier de Charlebourg, à la Garenne-Colombes : début des travaux Jun 8, 2020 - Jun 30, 2025
- Construction of lot 2 - Les Hallizées May 1, 2023 - Sep 30, 2025
- Work on public spaces at Jardin des Rails, rue Edouard Colonne and Place des Groues Oct 1, 2023 - Dec 31, 2025
- Odyssey project site - Les Miroirs site Dec 15, 2021 - Jan 31, 2026
- Redevelopment of the public spaces of the Place Carpeaux Jan 1, 2022 - Jan 31, 2028
Construction of lot 3 - La Forêt des Groues - ZAC des Groues
Nov 19, 2021 - Jun 30, 2024
Developer: LAMOTTE IMMOBILIER Architects: Sonia Cortesse, M'CUB architectes, Julien Beller Sonia Cortesse, M'CUB architectes, Julien Beller Contractor: ECM for structural work Location: 28 rue François Hanriot, northern sector of Les Groues, Nanterre
Perspective
Lot 3A: 108 multi-family housing units, a crèche, a craft workshop and 72 parking spaces on 1 basement level.
Lot 3B: 40 apartments, a business premises and 28 parking spaces.
We are fast approaching delivery of all housing units in both parts of the project. Deliveries have been delayed by a few months due to recurrent bad weather and an unforeseen change in the locksmith's company.
Technical witnesses have been validated in order to set performance levels for the facades. Secondary contractors are now finalizing their work in all units. Final work will now focus on the green spaces around the buildings.
Construction schedule:
- Start of works: February 2022
- Infrastructure (parking levels): June 2022
- Structural work: April 2023
- Secondary trades (interior): February 2024
- Delivery: before summer 2024
For any questions: riverain-idf@lamotte.fr - number: 01 43 25 62 89